City of Bend outlines street projects

POSTED: 12:38 PM PDT August 2, 2013 

Several sections of streets throughout Bend are scheduled for maintenance and repairs or will begin Capital Improvement Project construction during the week of August 4.

Signage and/or personnel will be in place to help control traffic.  Travelers should expect delays.  Please proceed through work zones with caution and thank you in advance for your patience.

Construction Schedule
Project dates are estimates based on favorable conditions; variances may occur due to weather or other unforeseen circumstances.

Start Date

Estimated
Duration

Location

From/To

Type of Work

Type of Closure

Hours

Note

Aug 5

12 Wks

Riverside Blvd

Tumalo Ave to Broadway

Riverside Ped/Bike Infrastructure Project:

RiversideFranklin.com

Lane shifts w/ two way traffic maintained

7am–6:30pm

Mon- Fri

Aug 4

5 Days

American Ln/Brosterhous

American Loop to Klahani

Asphalt Overlay

Rolling lane  shifts and detours

7pm – 7am

Night Work

Aug 5

4 Days

Wilson Ave

Third St to Centennial

Asphalt Crack Sealing

Signs posted

6am–4:30pm

Mon- Thur

Aug 5

4 Days

27th St

Kim, Williamson, Professional

Sidewalk ADA Ramps

Be aware of cones and signs

6am–4:30pm

Mon- Thur

 

 

 

 

 

For schedule updates and information about ongoing projects, please visit www.bendoregon.gov/cityprojects.